April 19 - May 9, 2011 The project continues


Master tub installed and plumbing connections done


5 ton AC unit installed and mechanical inspection completed.
 


Guest tub and plumbing connections

Fireplace chase wrapped and ready for stucco

Dormer warpped and ready for stucco

350 ft trench dug to rerun the electrical line for the water well.
 Rocky really enjoyed this job.

Trench from house to connect water line to well.

May 6, 2011 - Nik, Clint and Cole are vacationing NOLA and will be christening Cole on May 15th.

Ahh, our little Prince on his first visit to the
 property and his new playground.


Cole says "Gigi, can  I drive the golf cart?"


Clint looking at Cole enjoying riding the cart with Mom and Gigi.

 May 9,  2011
Preparing the base stucco coat

Applying base stucco coat to dormer


Roofers started Monday, May 9th


Applying stucco color.....Irish Coffee



Plumbers finalizing work and another inspection down....yeah!



Front view L-R:  master closet, entry, office than garage.