July 24 - 29 - Tiling and electrical almost completed, septic system installed


Gill's Water Works installing 320 ft of pipe for the septic system from the house to the front of the property




Water filtering


98% complete with tile, grouting will be done Monday & Tuesday


Sunroom


Rocky on a break and put together a dune buggy for our grandaughter Briley.
 Of course he had to ensure it was safe and not too fast for her.






Master Bedroom

Our tile contractor, Jeff Duet.

Guest bedroom

Our electricians, Mark Yaeger & Samual assembling and hanging 10 fans

Den

Dining room

Bonus room

Kitchen bar pendant lights facing den/patio

View from den into hallway leading to office,
guest bedroom & bathroom

Mark hanging one of two den fans. 

Stairwell leading to bonus room finally got painted,
still need to trim and put treads/risers & rails.

Patio fans and new tile


We're using this tile for the front porch and the utility slab. 


Friday, July 22, 2011

July 18th - 22nd - Painting, Caulking, Tiling & Electrical work

Sorry no new  pictures this week but staying very busy with lawn work, more painting and  caulking the trim. The tile work started Wednesday and the  electrican is back connecting the panel boxes and should be hanging all fixtures next week.  Once all the electrical is done we are  hoping to have the parish inspect and provide us a "temporary permit" which will allow us to have the a/c connected and turned on.  Then we'll have the wood floors delivered and installed within 2-3 days.  Remaining kitchen/bath cabinets are in (praying they fit this time)  and the appliances are in and will be delivered this week.  Cabinet/Trim carpenter will return after the floor is done.  This part is sooooo slow!

Thanks for your interest and  keeping up with our house progress and we promise to have photos next week.

Sandy & Rocky

Tuesday, July 12, 2011

Monday, July 11th - Garage Door installed

If only everything would be as fast and easy as the garage door.  However, we had to reorder a few cabinets that should arrive in a couple of weeks, cabinet trim/crown being installed and  started installing the interior doors.   The fireplace mantel guys should complete their work this week and the tile guy is scheduled for next Wednesday.


  A / C slab formed, poured and finished by the Daleos.
 Warning....do not attempt these jobs on your own! 




Friday, July 8, 2011

July 5th - 8th - More painting, started installation of cabinets & fireplace mantel.

Refrigerator, Stove & Oven cabinets

Storage cabinets & empty space is for the  wine cooler cabinet (had to reorder).

Sink, dishwasher & storage

Den bookcases/storage and start of mantel installation.

Guest bath partially installed

Steve, our cabinet & trim contractor

Utility Room

Painted garage, lots of tile and supplies

Bonus room painted

Lots more things to paint next week.  Doors & trim arrived Friday afternoon.



Monday, July 4, 2011

June 28 - July 4 - Stone & Vinyl work finished but the painting goes on and on!

Master bedroom

Master bath

Master bath shower

Kitchen

Dining room

Sunroom

Office

Guest bedroom/closet


Hall (looking from bedrooms in to den)

Vinyl soffit/facia and gutters completed